| Diesel-electric
equipment is also in hand for two double-ended ferries operating between
Hong Kong and the mainland and for a new ferryboat for Wallasey in
Cheshire. The latter vessel will be unusually attractive in appearance,
since it is designed to serve also for summer cruises off the coast,
and its propulsion system will be unique for ferries in this country.
TRANSFORMERS
Transformer ratings and voltages continued to rise. For instance
a 100,000-kVA 220/150/10-5-kV three-phase transformer group has
been built for the Netherlands; the 150-kV windings, which have
a fully insulated neutral, are fitted with an on-load tap changer
having a range of ±13 per cent in eighteen steps. A 100,000-kVA
231/110/11-kV three-phase group is in hand for Poland, and 52,500-kVA
transformers and 30,000-kVA groups are being built for 165-kV
three-phase service in Portugal. Anticipating still higher transmission
voltages, designs have been worked out for 300-kV and 400-kV systems,
and a 750-kV testing transformer has been made and installed in
the transformer shop.
For
large transformers with supplementary air-blast cooling, the use
of an individual self-contained fan-and-motor unit with each radiator
is a great advance.
The
shipping of big transformers still has its difficulties. When two
75,000-kVA 132/33-kV units for the B.E.A. had to go by road to Edinburgh
(Portobello) this year, the Ministry of Transport limited the gross
weight of the load to 150 tons and the height to 15 feet. A new
method of shipment was therefore adopted: the transformer tanks
were fitted with lugs at each end, and the road bogies attached
by links and jacks, which enabled the load to be lowered at low
over-bridges and raised on hump-backed ones. The Company has also
been active in promoting the use of interchangeable rail and road
bogies for direct attachment to the ends of large transformer tanks.
Two
large booster transformers for controlling the power flow in 132-kV
90,000-kVA feeders are in hand for B.E.A. substations in South Scotland,
one at Tongland and the other at Galashiels.
Among
the many arc suppression coils supplied for voltages from 33 to
132 kV is one of 3710 kVA built in 1945 for Russia. Some years earlier
the Grampian hydroelectric scheme had been supplied with three
coils, two acting as ordinary suppression coils for the 132-kV
and 33-kV systems respectively and the third arranged to compensate
for the mutual capacitance between the two systems, which run near
each other for a considerable distance.
Two
three-phase shunt reactors, each rated at 15,000 kVA, were supplied
in 1940 to neutralize the capacitance current on the 132-kV grid
feeders in the London area; they were switched in at times of light
load to prevent a rise of line voltage. In 1944 came the largest
reactor plant ever made in this country, a three-phase bank designed
to give an 18 per cent choke on a 90,000-kVA three-phase 132-kV
feeder.
|